PROJECT UPDATE:

April 14, 2024

Capital campaign: we're very excited to have now reached 74% of our goal. We've received pledges totalling $256k!

Construction update: There are discussions underway between Kathleen (or designer), Gibraltar (our contractor), and the city of Coquitlam. The goal is to reduce the costs from the most recent quote and meet building codes so that we can get our building permit. We don't yet have a date for when the construction will start but it will be 2 weeks after the building permit is issued

Once construction starts (or just before) we will have an orientation to the space to ensure everyone stays safe during construction. There will be "no go" zones in place. In addition if you wish to hold a meeting, due to the temporary loss of space, you will need to book ahead with Curt. Finally, it's been determined that the nursery will be moved to the loft during construction. We appreciate that the sound likely won't travel up there but you will be able to see into the service.

Finally one change that you will see shortly is that the coat rack in the small narthex will be moved to the hall. This was a planned change and we're very fortunate that we don't need a new rack and can repurpose the one we have. A big thanks to Ron Cooper for looking after this.

Cataloguing committee: Some of you may have noticed the Big Steel Box in the parking lot. This will be used to store some items during construction. We wanted to be sure to get it in good time so that we can start packing.

The organ: On a final note, we have previously let you know that the organ will be re-homed. We did place an ad with the RCCO on their website but have had no interest to date. We were in touch with someone who is willing to take the organ, fix it up, and find a new home for it. As it is quite possible he will take it next week, this is the last Sunday the organ may be with us.  Therefore we have asked Joanne to lead us in a prayer of thanksgiving for the gift of music it has brought to our community at both services on Sunday.

March 17, 2024

Construction Update:  We received a revised costing from our contractor, Gibraltar which has resulted in increased costs. This is not unexpected given that the original quote was provided last summer. We are now working with Kathlene, our designer, and Gibraltar to bring the costs down to very close to the original quote to keep the project on budget. As a result there will likely be some changes from the original plan and we will update you once those have been finalized. 

We are still waiting for our building permit to be issued and we’re hoping that may happen by early to mid-April.

Capital Campaign Update:  We have received pledges totaling $247k which is only $100k short of our goal! To date we have received $120k in pledges plus our $10k grant from the Anglican Foundation. The $130k has been invested in short term options to accrue interest until we need it.  In terms of our capital campaign, starting in mid-late April you should expect to hear more from us.

January 21, 2024

The renovation and capital campaign are moving forward with great excitement and anticipation. 

  • Construction updates:
    -We will be meeting with our contractor to discuss the final drawings so that the final estimate can be determined and the contract signed
    -The Diocese has signed the building permit application and we are waiting for its return so that it can be submitted as soon as the we have our contract signed
    -The Anglican Foundation is about to send us a $10k cheque which is their grant to us. We are also submitting the necessary paperwork to obtain the $100,000 loan from the Foundation 
    -On January 24, the Diocese will be re-confirming their support for our grant and loan as the grant from the Anglican Foundation was reduced by $5k. We are anticipating full support
    -The Cataloguing Committee, Chaired by Carla McGie, is starting to work on cataloguing all the items in the sanctuary in preparation for the construction as everything will need to be stored or re-homed
    -The Liturgical Committee, Chaired by Joanne Epply-Schmidt,  is beginning work on planning for services in the hall during construction
    -Our new chairs have been ordered and are being prepared. We should receive them in a few months

 

  • Capital Campaign updates:
    -We have received initial donations of $92k which is the first installment of the pledges totalling $192k. 
    -The official kick-off of the Capital Campaign was on Feb. 11. We're hoping for big win on our fundraising efforts
    -We now have a page set up on the St. Laurence website where you can get information and see these updates. Find us at: https://www.saintlaurence.ca/ministries/capital-campaign


As things are moving ahead quickly, you can anticipate hearing more about the Blessing our Future campaign and construction about every 2 weeks. If you have any questions, please contact Curt or a member of the Project Team.

 

December 7, 2023

Good news! The Anglican Foundation of Canada is giving us a grant of $10,000 and a loan of $100,000.  The Diocese of New Westminster will also be giving us a grant of $40,000 and a loan of $50,000 once it makes a technical amendment next month to its’ grant motion to include the actual amount of the Anglican Foundation grant.  That means Renovision is a go!